The Chatham Sanitary Pump Station #5 is located within the Second Street municipal road allowance Development over the past 54 years has seen the lands adjacent to the Second Street corridor crowded by the construction of the Chatham-Kent Civic Centre and Chatham-Kent Fire Services Station 1.  

At present, the structure of Pump Station No. 5 sits immediately in front of the Fire Station which creates an obstacle to continued operation and maintenance of the station.  The proposal will be to relocate the station to one of two proposed locations with an updated operational and design methodology which meets current engineering design best practices.

The Chatham Wastewater Pump Station #5 - Relocation Project has a total projected value of $350,000. The timeline for this project is November 2016 to March 2018.